“A contractor for Enugu State’s Smart Schools Project has taken to social media, claiming victimization. The contractor in question—identified as Sijibomi Ogundele, also known as Sujimoto—
… says the project was awarded below cost… That the Governor promised him another contract… And that rising costs forced him to abandon the work. And finally, that he’s heading to the EFCC to clear his name. But what do the facts actually show?”
 Evidence & Counterfacts Narration: “On July 2, 2024,   was awarded ₦11.4 billion to build about 20 Smart Green Schools. The government says they advanced him half of that sum—₦5.7 billion—upfront to speed up delivery. Yet, a year later, joint inspections by the Ministry of Works and the security agencies found most sites abandoned, some barely above foundation level. Reports show progress of only 5 to 30 percent across the sites, despite hundreds of millions released for each one. No materials on site. No workers. Poor workmanship. And the contractor is said to have ignored invitations to explain himself. Instead of lawful requests for contract review, he walked away.”
Context & Accountability Narration: “Government records show something more troubling. According to the Government, though Sujimoto presented a bond from Jaiz Bank, he diverted all payments into a different account—making accountability difficult. This shows premeditated intent to defraud, not hardship, the Government counter claims. That’s why the State petitioned the EFCC.
Debunker fact checking team confirms that, meanwhile, other Smart School contractors working under the same economic conditions have continued to deliver while negotiating for review and variations. Many of the smart schools’ campuses, such as the three in GTC Enugu, and the ones in:
Queens, New Layout
Ndeabor, Aninri LGA
Owo Nkanu
Ugwuomu Nike
Obe, Nkanu West
Umuome, Inyi, Oji River
Ubahu-Amankanu, Nkanu East
Umachi, Igboeze North
Amechi Idodo, Nkanu East
Essodo, Igboeze North
Alor-Uno, Nsukka
Nkerefi, Nkanu East
Ajiona Ovoko, Igboeze South
Ihe Obukpa, Nsukka
Iheakpu Awka, Igboeze South
Ihe Onuiyi, Nsukka
Ibeagwa Ezema, Igboeze South
Ibeagwa Nike, Enugu East
Iheaka, Igboeze South
Ugwogo Nike, Enugu East
Ovoko Ulo, Igboeze South
are at various stages of completion.
Conclusion: Narration: “Sujimoto had a clear contract. He received advance payment of billions of Naira. Instead of going into arbitration when he had difficulties, he abandoned the sites. Therefore, the verdict is clear: Sujimoto’s claims are misleading.
Since the government is determined to launch many of the Smart Schools are by September 2025, it is taking determined actions to deliver.